Piha R&R has received the following advice from Auckland Council Community Facilities:
- Les Waygood Park – refurbish amenity buildings at campground (Renewals funded)
- Remove the existing roof material off the male amenity building and replace with Terracotta tiles (to match the female toilets)
- Repair the soffits and replace guttering where required
- Remediate and paint all external joinery to a functional condition and replace a broken window latches.
- Remediate all areas of damaged “stucco” to match existing
- Replace existing kitchen amenity roofing with corrugated iron
- Replace the faulty toilets
- The work is scheduled to commence the week of 27 April 2021 and be complete by the end of May 2021 – the work is weather dependant
- Piha Wetland (LDI Capex funded)
- Installation of two picnic tables
- Removal of the existing old farm fence
- The work is scheduled to commence 1st May 2021 and be complete by 10 May 2021 – the work is weather dependant
- Piha Domain picnic tables (Renewals funded)
- Replacement of two picnic tables next to the playground (like for like). Due to be completed by early May.
Other project works currently underway at Piha include:
- Piha Domain amenity block
- oil and paint toilet amenity block – is scheduled for completion in early May 2021
Auckland Council Project Manager is Dana Price 021 569 794